Forecasting For Activity Cost Control
Fore Casting for Activity Cost Control For Project Management & control using only past records of cost & revenue incurred is not sufficient. Good managers should focus on future revenue, future cost & technical problems. Project Management Training & Advance Project Management Certification Budgeted Cost Budgeted cost is derived from detailed cost estimate prepared at the start of the project. Estimated Cost The estimated cost or forecast total cost in each category is the current best estimate of costs based on progress and any changes since the budget was formed. . Estimated total cost are the sum of cost to date, commitments and exposure. Cost Overruns:- Overruns in cost might be due to lower than expected productivity, higher than expected wages rates, higher than expected material cost or any other factor. Low productivity can be due to inadequate training or lack of required resource such as equipment & tools. Forecast Total...