Critical Path Method



In the above network diagram there are three possible paths

1) Start → A→C→E→End→5+3+2=10 Days

2) Start → B→D→E→End→4+6+2=12 Days

3) Start → B→D→F→End→4+6+6=16 Days

Out of three paths 3) is the longest as it takes 16 to deliver all three activities.

This is the critical path

This above process is called as critical path.

Crashing - Adding more resources to any activity on critical path activities.

Fast Tracking : Re - sequencing activities in the network diagram to gain time benefits.


Comments

Popular posts from this blog

Why Indian Companies Keep Appointing Ill-Equipped Project Managers—and End Up Paying the Price

Why Most PMO Divisions in Indian Companies Fail Within Two Years