Earned Value Management
Planned Value(PV)- Planned value refers to what the project should be worth at a particular point in the schedule. It is also referred as BCWS (Budgeted Cost of Work Scheduled).
Earned Value(EV)- It is the physical work completed to date and the authorized budget for that. It is also referred as BCWP(Budgeted cost of work performed).
Actual cost (AC)- It is the actual amount of money spent. It is also referred as ACWP( Actual cost of work performed).
Estimate at completion (EAC) -It refers to the estimated total cost of the project at completion.
CPI- It is cost performance Index .
CPI= EV/AC
If CPI is less than 1, this means the project is over budget.
BAC refers to budget at completion.
It is related to EAC
EAC = BAC/CPI
www.ebeescorp.com
ETC refers to estimate to completion.
ETC = EAC-AC
CV - refers to cost variance
CV= EV-AC
SV refers to schedule variance
SV= Ev-PV
Negative cost or schedule variance means the project is behind in cost or schedule.
SPI refers to schedule performance Index
SPI = EV/PV
VAC refers to variance at completion
VAC=BAC-EAC
Earned Value(EV)- It is the physical work completed to date and the authorized budget for that. It is also referred as BCWP(Budgeted cost of work performed).
Actual cost (AC)- It is the actual amount of money spent. It is also referred as ACWP( Actual cost of work performed).
Estimate at completion (EAC) -It refers to the estimated total cost of the project at completion.
CPI- It is cost performance Index .
CPI= EV/AC
If CPI is less than 1, this means the project is over budget.
BAC refers to budget at completion.
It is related to EAC
EAC = BAC/CPI
www.ebeescorp.com
ETC refers to estimate to completion.
ETC = EAC-AC
CV - refers to cost variance
CV= EV-AC
SV refers to schedule variance
SV= Ev-PV
Negative cost or schedule variance means the project is behind in cost or schedule.
SPI refers to schedule performance Index
SPI = EV/PV
VAC refers to variance at completion
VAC=BAC-EAC
Comments
Post a Comment