Why Indian Companies Keep Appointing Ill-Equipped Project Managers—and End Up Paying the Price
Indian companies often ask a painful question after a project goes wrong:
“What went wrong?”
More often than not, the answer is simple:
the wrong person was given the responsibility of project management.
Recently, I had an interaction with one such case.
A senior executive—holding the title of Vice President—was responsible for submitting an execution program to the project consultant.
On paper, the designation looked impressive.
On ground, the decisions reflected a complete lack of project understanding.
And this is not an isolated case.
I have seen many poorly equipped engineers climb to senior project roles, not because of competence, but because of time served—what I call experience without learning.
🚧 THE CONTRACTUAL REALITY (WHICH WAS ALREADY FLAWED)
The contract milestones were defined as:
-
25% financial progress in 10 months
-
50% financial progress in 14 months
-
75% financial progress in 17 months
-
90% financial progress in 20 months
-
100% completion in 21 months
Even this structure was questionable.
If a client allows 10 months to reach 25%, it is fundamentally illogical to expect the last 10% in just one month.
Such back-loaded milestones already indicate poor planning by the client.
But what followed was even worse.
❌ THE CONTRACTOR’S SELF-SABOTAGE
The contractor (for whom we were providing consultancy) instructed us to prepare a program showing:
~7% progress per month starting from the 3rd month—and continuing at that rate.
This single instruction exposed the inexperience of the senior project leadership.
Here’s why:
-
In real execution environments, 4% monthly progress is already optimistic
-
Across multiple sectors and projects, 2.5% per month is a realistic average
-
Early project months involve:
-
mobilization
-
approvals
-
drawings
-
procurement
-
learning curves
-
site constraints
-
Yet this project manager wanted to show almost three times the realistic progress, on paper. It is very important for a project manager to understand financial vs physical progress in projects
⚠️ WHY THIS IS DANGEROUS (NOT JUST WRONG)
If the client itself is expecting only ~2.5% progress in the first 10 months, why would a contractor commit to 7% on record?
Even if the contractor could achieve it, it would:
-
create unrealistic future expectations
-
invite penalties when progress normalizes
-
distort cash flow projections
-
damage credibility with the client
-
expose the company to contractual risks
This is not optimism.
This is corporate self-harm.
And this is exactly what happens when titles are valued more than technical judgement.
🧠 THE CORE PROBLEM: DESIGNATION ≠ PROJECT MANAGEMENT
Operating Primavera does not make someone a planner.
Holding a VP title does not make someone a project manager.
A real project manager understands:
-
productivity curves
-
learning effects
-
front-end constraints
-
financial vs physical progress mismatch
-
risk of over-commitment
-
consequences of paper promises
When such understanding is missing, companies risk:
-
liquidated damages
-
penalties
-
loss of trust
-
claims and counter-claims
-
reputational damage
All because someone wanted the report to look aggressive instead of being realistic.
🧭 WHY COMPANIES KEEP MAKING THIS MISTAKE
Indian companies often promote people based on:
-
years spent in the system
-
ability to agree with seniors
-
comfort with presentations
-
lack of resistance
Instead of:
-
execution exposure
-
decision-making maturity
-
risk awareness
-
ground experience
This creates a dangerous leadership layer—
high on authority, low on judgement.
🌱 THE WAY FORWARD
If companies want to protect themselves, they must:
-
Separate designation from capability
-
Appoint project managers who have:
-
executed real work
-
failed and recovered
-
learned productivity realities
-
understood financial consequences
-
-
Stop rewarding unrealistic optimism
-
Encourage honest, defensible planning—not aggressive fiction
Because in project management:
Over-commitment today becomes penalty tomorrow.
🧠 FINAL TAKEAWAY
Projects don’t fail because of lack of effort.
They fail because of bad decisions made by the wrong people at the top.
An ill-equipped project manager can risk an entire company—
not by doing too little,
but by promising too much.
Titles don’t deliver projects.
Judgement does.



Comments
Post a Comment