Project Time Management
Project Time Management is basically collection of following steps: 1) Activity Definition 2) Sequencing 3) Estimate resources & Duration 4) Develop Schedule & Control it Milestone List :- Project can't be controlled against single end point. There should be some intermediate control points. Management can check the project performance against those intermediate Milestones. Activity Definition:- Breaking down of WBS or big work into small and manageable activities. There are two sequencing diagrams or network diagrams. 1) Activity on Node 2) Activity on Arrow. Activity on Node or precedence Diagram Method :- Nodes represent activities and draw arrows to show the dependencies. Activity on arrow or Arrow Diagram Method :- Nodes are transition points (dependencies) and arrows represents activities.